Waterman Place

Tentative Start: October 7th*

Contact: David Meyer

Mobile: (314) 568-9854

Leritz Busy Bee paving is pleased to announce that we have been awarded the street resurfacing project on your subdivision street. This notice is to inform you of the scope of work and projected time frame, so you have the opportunity to plan accordingly.


Our work includes roto-milling half of the street down 2 inches, cleaning pavement, applying a tack coat or adhesive, and placing a new asphalt surface over the existing roadway.

Tentative Schedule


Monday, October 7th: Roto-Milling


  • We ask that all cars be moved by midnight
  • Any remaining cars will be towed
  • Entire street closed to traffic
  • Large construction equipment will cause additional noise


Tuesday, October 8th: Paving


  • Work will occur from 7:00 am - 5:00 pm
  • Entire Street closed to main traffic
  • Paving will occur on the main drive of the street
  • Work will start from the back and move to the front
  • Prepare for delays if leaving residence after 7:00 am
  • Street will be open after 5:00 pm, or when work is completed


Wednesday, October 9th: Paving


  • Work will occur from 7:00 am - 3:00 pm (tentative)
  • Entire Street will be closed to traffic
  • Paving will occur near both entrances to the street
  • We anticipate finishing by 3:00 pm
  • After completion, the street will reopen


Notes


  • Please be advised that we will apply a tack coat to the old surface to bond the new asphalt layer.
  • This is a very sticky black substance that will stain your automobiles and driveways, particularly concrete driveways.
  • Please do not drive through the tack coat and onto your driveways.

*We must have dry weather to perform this work. Rain or a threat of rain will cause us to postpone our work until the next weekday. Of course, if an emergency arises, we will stop our work and move out of the way for emergency vehicles.

To Help Plan Your Day, Here Are Some Reminders

Postpone Home Maintenance

Including Lawn Maintenance.

There will be no room for pickup trucks or trailers to maneuver.

Postpone Deliveries

Including Amazon, UPS, FedEx, appliances, furniture, etc., for the same reasons listed previously.

Do Not Run Sprinkles

Specifically on the days our crews are working. We cannot pave a wet street.

Do Not Let Pets Run Loose

They can burn their paws on the hot asphalt or get black goo on their paws and track it into your home.

Mark Exterior Systems

Including sprinkler systems, dog fences, and other items; they are the homeowner's responsibility.

Thank you for your confidence in our company. At Leritz Busy Bee, we know all things asphalt and paving. Our expert team is ready to work with you on new pavement projects, asphalt maintenance, & municipal asphalt projects. We're here to help!