Paradise Valley

Creightonwood

Tentative Start:  May 19th*

Contact: Jonathan Haarmann

Mobile: (636) 248-0638

Leritz Contracting is pleased to announce we have been awarded the street resurfacing project on your subdivision street. This notice is to inform you of the scope of work and projected time frame so you have the opportunity to plan accordingly.


Our work includes roto-milling of 2” of various areas on the street and patching, pavement cleaning and tacking, and then placing a new 2” asphalt surface over the existing roadway

Tentative Schedule


Tuesday, May 19th: Roto-Milling and Patching


  • Roto-Milling of various areas and patching.
  • Large construction trucks and equipment will be present, but the road will be open to local traffic
  • Delays may occur at times due to construction activity


Wednesday, May 20th: Asphalt Work


  • Asphalt work is scheduled to proceed from 7:00 AM - 5:00 PM
  • The road will be closed to traffic
  • Prepare for delays if you leave your house after 7:00 AM
  • You will be free to use the streets after about 5:00 PM or when the work is complete


Notes


  • Please be advised that we will apply a tack coat to the old surface to bond the new asphalt layer.
  • This is a very sticky black substance that will stain your automobiles and driveways, particularly concrete driveways.
  • Please do not drive through the tack coat and onto your driveways.


*We must have dry weather to perform this work. Rain or a threat of rain will cause us to postpone our work until the next weekday. Of course, if an emergency arises, we will stop our work and move out of the way for emergency vehicles.

Rockfern Drive and Court

Tentative Start:  May 18th*

Contact: Jonathan Haarmann

Mobile: (636) 248-0638

Leritz Busy Bee paving is pleased to announce we have been awarded the street resurfacing project on your subdivision street. This notice is to inform you of the scope of work and projected time frame so you have the opportunity to plan accordingly.


Our work includes roto-milling of 2” – 0” from the curb line out to the center of existing asphalt, pavement cleaning and tacking, placing a new asphalt surface over the existing roadway, installing new asphalt curbs, and backfilling of the curbs.

Tentative Schedule


Monday, May 18th: Roto-Milling


  • Roto-Milling of various areas
  • Large construction trucks and equipment will be present, but the road will be open to local traffic
  • Delays may occur at times due to construction activity


Tuesday, May 19th: Asphalt Work


  • Asphalt work is scheduled from 7:00 AM - 5:00 PM
  • The road will be closed to traffic
  • Prepare for delays if you leave your house after 7:00 AM
  • Large construction trucks and equipment may be present
  • You will be free to use the streets after about 5:00 PM or when the work is complete


Notes


  • Please be advised that we will apply a tack coat to the old surface to bond the new asphalt layer.
  • This is a very sticky black substance that will stain your automobiles and driveways, particularly concrete driveways.
  • Please do not drive through the tack coat and onto your driveways.


*We must have dry weather to perform this work. Rain or a threat of rain will cause us to postpone our work until the next weekday. Of course, if an emergency arises, we will stop our work and move out of the way for emergency vehicles.

To Help Plan Your Day, Here Are Some Reminders

Postpone Home Maintenance

Including Lawn Maintenance.

There will be no room for pickup trucks or trailers to maneuver.

Postpone Deliveries

Including Amazon, UPS, FedEx, appliances, furniture, etc., for the same reasons listed previously.

Do Not Run Sprinkles

Specifically on the days our crews are working. We cannot pave a wet street.

Do Not Let Pets Run Loose

They can burn their paws on the hot asphalt or get black goo on their paws and track it into your home.

Mark Exterior Systems

Including sprinkler systems, dog fences, and other items; they are the homeowner's responsibility.

Thank you for your confidence in our company. At Leritz Busy Bee, we know all things asphalt and paving. Our expert team is ready to work with you on new pavement projects, asphalt maintenance, & municipal asphalt projects. We're here to help!